Basic requirements for transverse cutting lines of silicon steel sheets:
1. Cross cutting line operators should have a high level of mechanical and electrical basic knowledge, and undergo automatic control (numerical control) training. Only after passing the examination and obtaining the "Cross cutting Line Safety Operation Certificate" can they work independently.
2. Cross cutting line operators must participate in crane safety training (including the use of cranes, lifting equipment, etc.) and obtain the "Crane Safety Operation Certificate" after passing the examination.
Preparation work for silicon steel sheet transverse cutting line:
1. Turn on the gas source, and when the air pressure reaches 6 Pa, open the drain valve to drain the water. Only after the water is drained can the machine be ready to start.
2. Check the oil level of the oil mist device, which should be between 1/3-2/3 of the oil cup. If it is insufficient, it should be replenished. When replenishing oil, be sure to turn off the air source and empty the compressed air.
3. Lubricate the guide rail and screw, and wipe off any oil stains.
4. Start the power test and check if all sensors are functioning properly and if the fastening bolts are safe and reliable.
Working process of silicon steel sheet transverse cutting line:
1. Carefully read the drawings, input data such as width and length according to regulations, and review them. Adjust the width of the guide rail, the position of the punch press, and the position of the stacking platform according to the requirements.
2. Measure the actual width of the silicon steel sheet coil to be cut, with a measurement accuracy of 0.05 millimeters. Check the width tolerance, S-degree, and waviness of the coil, which must not exceed the standard.
3. Loading, manual trial cutting, taking pieces, and comparing them with the drawings can only be automatically cut after passing inspection.
4. During the cutting process, the operator should closely monitor the operating conditions of each conveying part. If there is any blockage, stop the machine immediately for handling.
5. During the normal operation of the equipment, do not insert any part of your body, such as your arms, under the stacking platform or other conveying parts to prevent accidents. If adjustments are needed, they should be made while the machine is stopped.
6. Do not place tools, pieces of material, or other debris on the equipment during operation.
7. When using a crane to load and unload material rolls, be sure to operate according to regulations to prevent accidents.
8. When lifting finished products, it is necessary to adjust the balance of the material platform, start slowly and fall slowly, and use anti slip pads to prevent injury.
9. When the waste bin is full, it should be replaced in a timely manner.
10. During the work process, if there is any abnormality in the equipment, it should be immediately stopped for processing, the equipment maintenance personnel should be notified, and records should be kept.
11. Carefully fill in the handover record during the shift handover.
The transverse cutting line for silicon steel sheets has been completed:
1. At the end of the work, the power and gas sources should be turned off.
2. Wipe the equipment clean and clean the area around it.